南奥兰治县可靠性增强 (SOCRE) Project
我们的使命是提供我们的3.7 million customers with clean, safe and reliable energy. 要做到这一点, we continue to modernize and upgrade existing substations and infrastructure, 这样你就能得到你应得的可靠能源. The SOCRE project improves electric reliability in South Orange County. SOCRE项目于12月15日获得批准, 2016, 加州公用事业委员会(CPUC). Construction on this project began in 2017 and is expected to be completed in 2024.
项目简介
The SOCRE project will increase the reliability and operational flexibility of 西班牙&E’s South Orange County 138-kilovolt (kV) system and reduce the risk of power outages. Aging electric infrastructure in South Orange County is being upgraded, including the Capistrano Substation in the City of San Juan Capistrano and the existing transmission line network serving the area.
塔莱加变电站输送的电力, 位于海军陆战队彭德尔顿营地, is transmitted to seven distribution substations over a 138-kV transmission network; Capistrano, 有些孩子, 玛格丽塔, 皮科, 圣马特奥市, 米申维耶霍牧场和特拉布科. The SOCRE project will improve reliability by providing a second 230-kV power source to 西班牙&E的南奥兰治县服务区. 卡皮斯特拉诺变电站, 建于1918年,最后一次重建是在1940年, will be modernized including the aging infrastructure between the Talega and Capistrano Substations.
西班牙&E will send community members advance notifications and project updates through the US Postal Service, 电子邮件, 挨家挨户的宣传和新闻媒体. 下面你会发现 项目进度, 可靠性的好处, 常见问题, the project permitting process and project contact information. We too, live and work in the communities where construction is taking place. We respect your streets and neighborhoods and will take care when driving and working in the surrounding communities.
项目的好处
- 提高现有电力系统的可靠性
- Modernizes electric transmission system and replaces outdated equipment
- Replaces wood poles with steel poles to reduce fire risks
- Meets current and future energy needs of local homes and businesses
- 允许操作灵活性
- 符合联邦和州可靠性标准
施工进度
Reconstruction of the San Juan Capistrano Substation began in July 2017 and was the beginning of an approximately six-year construction schedule. 自2019年初以来, power lines surrounding the Capistrano Substation are being installed and configured. 也, some of the existing transmission structures between the Capistrano and Talega Substations are being replaced with upgraded, 容量增加的现代建筑.
施工进度 | |
---|---|
2012 – 2017 | 项目允许 |
2017 – 2022 | 重建和升级Capistrano变电站 |
2019 – 2024 | Replace and upgrade a transmission line with phased completion |
2020 – 2024 | Replace existing structures with taller, new steel poles |
常见问题
The project is in San Juan Capistrano, San Clemente and the unincorporated areas of Orange County. The outdated substation in San Juan Capistrano is being rebuilt and upgraded. One of the transmission lines that connects the Capistrano and Talega substations is being upgraded to provide added reliability and operational flexibility.
The 南奥兰治县可靠性增强 Project is necessary to maintain reliability in the South Orange County communities. By replacing outdated and aging infrastructure in the area, 西班牙&E will be able to maintain safe and reliable service to its South Orange County customers. In addition, the added capacity will accommodate future growth.
西班牙&E developed the ‘preservation alternative’ to save and restore the former utility structure that was originally built in 1918. Keeping and restoring a portion of this structure was a major request from several local community stakeholders. The CPUC approved this alternative in their final decision dated December 15, 2016.
西班牙&E is replacing the existing 138/12-kV substation that was last rebuilt in the 1940’s with a new 138/12-kV gas-insulated substation. 另外, there will be a new 230/138-kV gas-insulated substation built within the substation site. Once the new 138/12-kV gas-insulated substation is in service in the lower yard, the existing 138/12-kV substation will be decommissioned and the 230/138-kV gas-insulated substation will be built in the upper yard. And the majority of the existing wood poles to the east and west of the site will be removed and the lines will be undergrounded.
项目允许:
建议者环境评估
建议者环境评估, Volume II of II, PUBLIC Version
CPUC监管程序
西班牙&E filed an application with the CPUC for the SOCRE project in May 2012 and the CPUC application for SOCRE was filed May 18, 2012.
CPUC范围界定过程日期:
-
公开会议于2013年1月23日至24日举行
-
公众评议,2013年1月9日至2月22日
-
EIR草案-意见征询期于2015年4月10日结束
-
Additional Draft 环境al Impact Report (DEIR) comment period ended on September 24, 2015
-
最终决定于2016年12月15日做出
CPUC的SOCRE项目网站
进入CPUC网站
Para information Español
西班牙的传单
全球十大博彩公司评级/了解更多信息
施工热线1-833-201-5218
Erik Weigand
公共事务经理
南奥兰治县可靠性增强
(949) 577-0005
(电子邮件保护)